The installation process took 26 weeks, according to Allison. "We had to phase the equipment into our operations," he explains. "The first phase focused only on our direct-to-consumer business."
To meet the needs of Gymboree's direct-to-consumer business, EuroSort designed the equipment to sort up to 22,000 orders per day, or 14,400 pieces per hour at peak capacity. Gymboree's average, however, is close to 4,600 orders per day, a number the sorter can easily handle.
The ESF sorter has 372 destinations, one induction area, four manual induction stations, an omni-directional scanner and vision detection system, a double/double chamber consolidation chute, and 372 distinct sorter chambers and packing out chambers.
The sorter receives its instructions via Gymboree's WMS system, which communicates with middleware software provided by AL Systems, Rockaway, N.J. The WMS sends a wave sort for 1,400 orders at a time.
"The wave criteria sets orders, then launches a wave to the AL Systems application," says Allison. "The system calculates where the orders should go based on dimensions."
From there, products move through six scanners for identification; EuroSort reports back to AL Systems what it "sees," and the AL Systems software tells the sorter which chute to send orders to.
"Once orders are complete, the sorter makes sure products have been inducted, then closes the chute. The software tells pickers what size box to use. Pickers scan the bar code on the box and send it to the packing lane," explains Allison. "Orders are cycled out in about an hour, then the next wave of orders comes through."
The EuroSort installation was successful because all three parties involved worked together effectively, says Howard Eisenberg, president, EuroSort. "Bi-weekly meetings lent an air of cooperation," he notes. "This project was a textbook install -- all the components fell into place easily."
The new sorter turned out to be exactly what Gymboree needed to keep up with its rapid growth. "Over the past year, we've seen a 19-unit-per-hour increase in productivity, which amounts to a 70-percent improvement," says Allison. "And our cost per unit decreased by about 70 percent."
Still, the project was not without its nail-biting moments. Initially, the team planned to be up and running by August 2005, but pre-launch tasks delayed installation until November.
"We spent most of November working out bugs, but by December we were operating at 60-percent efficiency," says Allison. "By January, we were up to 80-percent efficiency; we're still working to balance out our line properly."
Having the project run into the busy holiday season posed a challenge for the company, but Allison says it actually saved the day. "This was definitely the worst time of year to implement new equipment, but I'm thankful that we did," he says.
The project timing wasn't ideal and added pressure to the project, agrees Eisenberg. "In the end, however, it fell back on Gymboree to complete training and hit the ground running," he says. "They took necessary steps to ensure they would be ready -- not all companies are that proactive."
Gymboree is so pleased with the new sorter's results, it held a contest to name the equipment. The winner? "GUSS" -- Gymboree Corporation Unit Sortation System.
So while the holiday season wasn't an ideal time to bring GUSS on line, Gymboree can't imagine operating without it.
"It was a risky move," Allison admits, "but we knew the method we were using before wasn't cutting it."